Resolution 84/2012/R/EEL – Technical features for LV and MV power plants to ensure the security of the national electricity system

https://encrypted-tbn0.gstatic.com/images?q=tbn:ANd9GcQASGR94r0OLsAcSUjiHLlCR51o9IhDniysbhTmHS9CNHcJtXFbscPkNQgY  A70

Resolution 84/2012/R/EEL Technical features for LV and MV power plants to ensure the security of the national electricity system

The resolution 84/2012/R/EEL approved new annexes to the Terna network code, and particularly Annex A70, which introduces requirements for power plants connected to MV and LV networks. The resolution also defines the deadlines to implement these requirements to power plants, including a retrofit for existing power plants to avoid critical situations on the electric network by next summer.

 

On March 8, 2012 the Authority for Electric Energy and Gas published on its website the resolution 84/2012 / R / EEL "Urgent interventions in power plants, particularly referring to distributed energy generation, to ensure the security of the national electricity system " that defines also implementation procedures and deadlines of Annex A.70 to TERNA s.p.a. company network code according to "Technical regulation of the distributed energy generation system requirements.".

The resolution 84/2012 / R / EEL has been modified in 2013 with integrations and modification according to the resolutions 165/2012 / R / eel, 344/2012 / R / eel, 562/2012 / R / eel and 243/2013 / R / eel.
The compliance of the Annex A.70 and IEC technical rules is a restriction for the activation and maintenance of the connection of each power plant .

Therefore, the new power plants which will enter in service from 1 April 2012 and which do not meet the requirements of Resolution 84/2012 / R / EEL, integrated and modified by resolutions 165/2012 / R / EEL, 344 / 2012 / R / EEL and 562/2012 / R / EEL, cannot enter in service.

 

Typology

Network voltage

Period of entry in service of the installation connected to the electric network

Date of submission of the complete request of connection

Adaptation to respect in compliance with technical rules

a)

MV

from April 01/2012 to June 30/2012

 

Installation complies with annex A.70 (only paragraph 5 and 8)

b)

MV

from July 01/2012 to December 31/2012

 

 

Installation complies with annex A.70 (entirely)

 

c)

MV

After December 31/2012

Case c.1)

by December 31/2012

Installation complies with technical rules IEC 0-16 third edition with exception of paragraph 8.8.5.3, letters a), b), c), d), e), f), paragraph 8.8.6.1, letters c), d), e), paragraph 8.8.6.3.1, paragraph 8.8.6.3.2, letters a), b), c), d), e), paragraph 8.8.6.5, paragraph 8.8.8.2 and paragraph 8.10, points 2) e 3), as well as all the annexes referring to these paragraphs

Case c.2)

from January 01/2013 to Ma31/2013

Installation complies with technical rules IEC 0-16 third edition with exception of paragraph 8.8.5.3, letters e), f), paragraph 8.8.6.1, letters c), d), e), paragraph 8.8.6.3.1, paragraph 8.8.8.2 and paragraph 8.10, points 2) e 3), as well as all the annexes referring to these paragraphs

.

Case c.3)

from April 01/2013 to September 30/2013

Installation complies with technical rules IEC 0-16 third edition with exception of paragraph 8.8.5.3, letters e), f), paragraph 8.8.6.1, letters c), d), e) and paragraph 8.10, points 2) e 3), as well as all the annexes referring to these paragraphs

Case c.4)

after September 30/2013

Installation complies with technical rules IEC 0-16 third edition with exception of paragraph 8.10, points 2) e 3), as well as all the annexes referring to these paragraphs

d)

LV

from April 01/2012 to June 30/2012

 

Installation complies with annex A.70 (paragraph 5 notwithstanding section 4.1.d of resolution 84/2012/R/EEL calibration for protection of frequency 49-51 Hz)

e)

LV

from July 01/2012 to December 31/2012

 

Installation complies with annex A.70 (entirely with the exception of paragraph 7.2.1) and with technical rules IEC 0-21 including modification (entirely with exception of paragraph 8.5.1)

f)

LV

after March 31/2012

 

Installation complies with technical rules IEC 0-21 in according to integrations and modifications of the IEC 0-21 interpretaion document; modification V1

g)

MV (with rated power >50 kW )

by March 31/2012

 

Installation to be adapted to annex A.70 (only paragraph 5 and 8) by 31.03.2013

 

*  

by date of entry in service of a power plant, it means the date of start up as defined in the Integrated technical rules on the operative connection (TICA) and in guidelines on the connection to the Enel Distribuzione electric network.

In the connection request, in the case of power plants that must realize a partition into lots or subdivisions with different dates of entry in service, the regulations described on the chart are applied differently for single sections in relation to the date of entry in service.

Aggiornamento 2013 Delibera 84/2012/R/EEL Deliberazione 84/2012/R/EEL
 
 
CONTACTS
EMA Switchboard
by EMA Quadri srl
Via Matteo Ricci, 14A
Palombina Nuova
60126 Ancona (AN)
Italy
P.IVA 02377120429
REA 182718
Tel: (+39) 071 888857
Fax: (+39) 071 888818
PRIVACY POLICY
By clicking the "Send" button I declare to have read and approved the rules of personal data processing listed in the document Privacy
 
web master,web designer, SEO, web marketing, by COMPUTER Plus
Norma:
Per scaricarlo compila i campi qui sotto e premi il pulsante ""richiedi"". Il documento ti verrà spedito via mail all'indirizzo indicato.
INFORMATIVA SULLA PRIVACY
Cliccando sul pulsante "Invia" dichiaro di aver letto e di approvare le norme del trattamento dei dati personali elencate nel documento Privacy